On 24 July 2021 we plan to organize a traditional annual disaster recovery testing of Moscow Exchange and our clients’ systems. During this test we will emulate the main MOEX data center unavailability and transfer trading to the backup data center.

Testing schedule (MSK time zone):

 

Part I. Start of trading day at DSP datacenter:

  • 10.00 – 10.30 – Clients connect via Universal scheme and ConnectME scheme to trading systems at the Dataspace datacenter.
  • 10.30 – 11.30 – Trading period for all markets, Dataspace runs as primary datacenter. Money market will only be available for connectivity test, no auctions will be held.
  • 11.30 – 12.30 – DSP failure emulation: network access to DSP will be cut down.

 

Part II. Continuation of trading day at M1 datacenter:

  • 12.30 – 13.00 – Clients connect to trading systems at the M1 (All trading systems will be unavailable from colocation zone at the DSP datacenter and ConnectME schemes terminated at the DSP datacenter during this stage)
  • 13.00 – 14.00 – Continuation of trading day for all trading systems. M1 runs as primary datacenter, DSP datacenter is unavailable.

 

Part III. Production configuration restoration:

16:00 – 18:00 – participants check ability to connect to systems in all datacenters and via all connection schemes, including colocation.

The final schedule will be sent later along with the beginning of the testing participants registration.

Contacts for media
+7 (495) 363-3232
Public Relations Department
Contacts for clients
+7 (495) 232-3363
Feedback form