01.11.2016 11:40
Final testing of MOEX migration to new data center on 5 November 2016
We would like to remind you that the final testing of the MOEX infrastructure migration to the new DataSpace1 data center will take place this Saturday – 5 November 2016.
Please send your applications for participation till 17:00 MSK on 2 November 2016.
For more information visit http://moex.com/n14121
Note the following:
- Trading systems of the following markets will be available for the connectivity check: FX, Derivatives, Equity & Bond, Money (Loans & Deposits), MOEX Board.
- MOEX will be generating the background activity on the FX, Derivatives, Equity & Bond markets. We invite all the trade participants to provide test load from their side.
- All the production connection protocols will be available, including the FAST data feeds.
For further information, please contact the Public Relations Department at (495) 363-3232.